Progress Chart (from 1/10/07 to 30/07/08)
Bldg. No.10, Clover Bldg. No. 11, Woodbine Bldg. No. 12, Drewberry
Act.     Act.     Act.    
Dates     Dates     Dates    
of Slab           of Slab           of Slab          
casting           casting           casting          
                             
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
                               
26.10.07 3rd Slab         14.10.07 3rd Slab                  
06.10.07 2nd Slab         24.09.07 2nd Slab     13.09.07 2nd Slab    
10.08.07 1st Slab     14.08.07 1st Slab     05.08.07 1st Slab    
26.06.07 Stilt Column     17.07.07 Stilt Column     26. 06.07 Stilt Column    
21.05.07 PCC       24.05.07 PCC     PCC      
10.05.07 Plinth       16.05.07 Plinth     20.05.07 Plinth      
  Stub Column     Stub Column   Stub Column    
19.03.07 Raft       31.03.07 Raft     06.04.07 Raft      
 
Slab Slab   Slab
Casting Casting   Casting
  -- Progress of current MONTH   Progress of Previous Month
(  OCT - 2007) ( SEP - 2007)
  -- Progress of Previous to previous month   Progress upto Previous to previous month
( AUG - 2007) (upto JUL - 2007)